Spatial reconfiguration played a pivotal role, with CORDOS demonstrating flexibility in adjusting plans for the display room. This involved canceling a planned ramp location and reorganizing the south side of the building. A notable feature of the construction included the installation of a 10-inch concrete floor, epoxy finished in the display room. Notably, dock doors were replaced with a separation wall and storefront windows to create distinct spaces, optimizing the layout for functionality and aesthetics.
The project timeline was a challenging but successful ten months, commencing in January 2023 and culminating in the grand opening on October 12th, 2023. CORDOS adeptly navigated unforeseen challenges, demonstrating resilience and adaptability to meet the stringent deadline. The financial overview revealed a total project investment of $1.5 million, encompassing various aspects of construction, remodeling, and state of the art upgrades.
The bidding process, a pragmatic 60-day endeavor facilitated by the trusted architect Filoramo Talsma, played a crucial role in securing CORDOS involvement in the project. This collaboration underscored the importance of effective project management, strategic planning, and a commitment to meeting the high standards set by the client.